Peimann Khotoot Gostar Current Projects

Item Client Project Name Technical Particulars Progress
1 (KzREC) KHUZESTAN REGIONAL ELECTRIC Co. AOC & RDC Dispatching Centers 79.58% 
2 (Isfahan Metro) Isfahan Metro SCADA & Dispatching 68% 
3 (Tehran Metro) Tehran Metro, Line 4 SCADA 50.99% 
4 (KREC) Shahmaran DCS for AIS 230kV S/S 85.33% 
5 (FREC) Shiraz Metro Substation DCS for GIS 66kV S/S 25.68% 
6 (FREC) Shiraz University Substation DCS for GIS 230kV S/S 71.31% 
7 (KzREC) Khuzestan DCS for 10 AIS 132kV S/S 91.55% 
8 (IPDC) Kord Koy,Mazandaran DCS for AIS 230kV S/S 70% 
9 (IPDC) Hamedan DCS for AIS 63kV S/S 70% 
10 (IPDC) Somesara DCS for AIS 63kV S/S 70% 
11 (IPDC) Babol DCS for AIS 63kV S/S 70% 
12 (IPDC) Tehran DCS for 2 GIS 63kV S/S 70% 
13 (MREC) Gonband - Mazandaran AIS 63kV Substation 46.42% 
14 (EREC) Esfahan - Kolandezh AIS 230kV Substation 34.18% 
15 (EREC) Chehelsotoon AIS 230kV Substation 79.58% 
16 (HREC) BandarAbbas, Amirabad Ghaffari 2 AIS 132kV Substation 87.24% 
17 (KREC) Torbat Jam AIS 132kV Substation 99% 
18 (KREC) Farouj AIS 132kV Substation 93.89% 
19 (KREC) Bojnourd AIS 132kV Substation 85.76% 
20 (Tehran Urban) Tehran DCS for 3 AIS metro substations s/s 58.41% 
21 (TREC) Tehran Regional Electric Company DCS for 10* AIS 63KV s/s 22%